The following is an excerpt from a Texas Department of Transportation press release regarding planned construction and maintenance projects for Abilene and Taylor County from Sept. 30 to Oct. 4:

Abilene Area Office construction projects:

  • I-20 frontage roads from Pine Street to Loop 322: Crews continue work on frontage roads, turnarounds and ramps. Drivers should use caution and follow warning signs and traffic control devices.
  • Loop 322 from I-20 to the Waldrop Interchange: Crews are completing paving work and preparing for striping and guard rail installation. Drivers should expect intermittent daytime lane and ramp closures.
  • Rainy Creek Bridge, E. US 80 east of Loop 322: Work to replace the bridge continues. Traffic is limited to one lane in each direction.

Taylor County Maintenance Office projects:

  • US 277 from FM 3438 to FM 1235: Repair pavement edges.
  • FM 89 between Rebecca Lane and Robertson Drive: Silt removal, ditch cleaning and storm drain repair work continues. Some lane closures will be necessary.